H. G. R. Mews Community Centre replacement
Construction for the new community centre in Mundy Pond Park, to replace the H.G.R. Mews Community Centre, is well underway.
Since Fall 2019, staff have been working to advance the design of the new building, incorporating what was heard through the engagement processes in 2018 and 2019.
Check out the visuals in the document library including an updated exterior rendering, the gymnasium with the elevated walking track, and the leisure pool, in addition to the other visuals added throughout the project.
Construction for the new community centre in Mundy Pond Park, to replace the H.G.R. Mews Community Centre, is well underway.
Since Fall 2019, staff have been working to advance the design of the new building, incorporating what was heard through the engagement processes in 2018 and 2019.
Check out the visuals in the document library including an updated exterior rendering, the gymnasium with the elevated walking track, and the leisure pool, in addition to the other visuals added throughout the project.
-
H.G.R. Mews Community Centre - Project Update
Share H.G.R. Mews Community Centre - Project Update on Facebook Share H.G.R. Mews Community Centre - Project Update on Twitter Share H.G.R. Mews Community Centre - Project Update on Linkedin Email H.G.R. Mews Community Centre - Project Update linkThe new H.G.R. Mews Community Centre is getting closer to completion. During the Commissioning Phase of the project, which started in late September, the Contractor had some issues with equipment delivered to the site from the manufacturer. Unfortunately, we ended up with faulty equipment and as a result we have encountered a delay in the project. We are pleased to report that the new equipment has arrived on site and the Contractor is now able to continue outstanding Mechanical Commissioning required for the building and the pool. While this work is on-going, the Contractor is working concurrently on addressing deficiency items and ramping up for a final cleaning of the building.
Recreation staff are working on their move transition plan from the olds Mews to the new Mews and finalizing details on programming for Winter 2025.
We anticipate that the new Mews will be opening early in 2025 to the public. Please stay tuned to our social media feeds and the Engage for further information regarding the public opening of the facility. We can't wait to welcome you to this new and beautifully designed building!!!
-
H.G.R. Mews Community Centre - Project Update
Share H.G.R. Mews Community Centre - Project Update on Facebook Share H.G.R. Mews Community Centre - Project Update on Twitter Share H.G.R. Mews Community Centre - Project Update on Linkedin Email H.G.R. Mews Community Centre - Project Update linkAs we approach the end of August and get ready for the Labour Day Weekend and Back to School, we are getting closer to the completion of the new Community Centre for Mundy Pond Park.
The Contractor is working on completing interior finishes and tile work for the pool and associated pool equipment. We are waiting on the arrival of the glass for the sport courts and final sanding and painting of the Gymnasium floor. Furniture for part of the administrative area has been installed on site, and we are awaiting the remaining furnishings for the remainder of the building fit up.
While we still remain behind schedule due to circumstances beyond our control, the Contractor is getting ready to begin the commissioning process in mid-late September. We anticipate that the commissioning process for the building will take approximately 1 month to complete.
The City of St. John's is excited to see this build close to completion. Further information regarding a grand opening for the building will be posted here and, on our website, and social media feeds. We look forward to welcoming everyone to this beautiful new facility!!
-
H.G.R. Mews Completion Date - Summer 2024
Share H.G.R. Mews Completion Date - Summer 2024 on Facebook Share H.G.R. Mews Completion Date - Summer 2024 on Twitter Share H.G.R. Mews Completion Date - Summer 2024 on Linkedin Email H.G.R. Mews Completion Date - Summer 2024 linkThe completion of the new H.G.R. Mews Community Centre is anticipated to be late Summer 2024. Work at the site continues, but supply chain issues have impacted the schedule due to delayed delivery of equipment required to complete the build. Additionally, there have been consistent and continued skilled trades labor shortages which have contributed to the schedule delay.
Further information about the grand opening of the facility will be posted here and on our social media outlets as soon as it is available.
-
New completion date - Spring 2024
Share New completion date - Spring 2024 on Facebook Share New completion date - Spring 2024 on Twitter Share New completion date - Spring 2024 on Linkedin Email New completion date - Spring 2024 linkThe construction of a new facility to replace the aging H.G.R. Mews Community Centre is approximately 60% complete and the facility is anticipated to open to the public in late spring 2024.
When construction began, the target for opening to the public was fall 2023, but due to issues around the availability and delivery of steel, the target opening date has been adjusted to late spring 2024.
The cost to construct the new facility remains on budget at $33,597,250 and is federally funded by the Canada Community Building Fund previously known as the Federal Gas Tax Fund.
Several significant milestones have been reached to date, including the completion and opening of the $1 million inclusive playground, funded by Canadian Tire Jumpstart Charities.
Once complete, features of the 60,000 square foot community centre will include:
• 25 metre, 6 lane swimming pool with a climbing wall
• leisure pool with water features
• steam room
• full-size gymnasium
• indoor walking track
• convertible courts for squash, handball, or racquet ball
• dedicated space for the Boys and Girls club and the REAL Program
-
H.G.R. Mews Centre Replacement: Project Update
Share H.G.R. Mews Centre Replacement: Project Update on Facebook Share H.G.R. Mews Centre Replacement: Project Update on Twitter Share H.G.R. Mews Centre Replacement: Project Update on Linkedin Email H.G.R. Mews Centre Replacement: Project Update linkConstruction for the new community centre in Mundy Pond Park, to replace the H.G.R. Mews Community Centre began in September and is well underway. The Jumpstart Inclusive Playground, which was gifted to the City by Canadian Tire Jumpstart Charities, is also under construction. The universally accessible Jumpstart Inclusive Playground will open in Spring/Summer 2022, and the new community centre will open to the public in Fall 2023.
Rendered images of the new community center, an overview of amenities, and background information regarding the H.G.R Mews Centre replacement project can be found on the page
The Jumpstart Playground was announced in July 2019. The new inclusive playground will further enhance the park as a destination for outdoor recreation by providing imaginative and accessible spaces where children of all abilities can play together.
The costs of playground equipment and rubber surfacing, valued at approximately $1 million, are funded by Jumpstart, with the City providing the land and costs associated with site preparation.
The total cost to replace the Mews Community Centre is $33,597,250 and is federally funded by the Canada Community Building Fund previously known as the Federal Gas Tax Fund. The program funding is administered and distributed by the Government of Newfoundland and Labrador to fund local infrastructure priorities such as public transit, wastewater, drinking water, roads, and buildings.
-
Mundy Pond Park Closed During Construction
Share Mundy Pond Park Closed During Construction on Facebook Share Mundy Pond Park Closed During Construction on Twitter Share Mundy Pond Park Closed During Construction on Linkedin Email Mundy Pond Park Closed During Construction linkMundy Pond Park is closed until September 2023 to facilitate construction of a new facility to replace the H.G.R. Mews Community Centre.
The Mundy Pond trail system, dog park and skate park remain open during construction. The amenities that remain open can be accessed:
- At the corner of Mundy Pond Road and Blackler Avenue
- Off of Melville Place
Parking is available along Blackler Avenue, and at the gravel parking lot across from the existing H.G.R. Mews Community Centre. Trail access at the gravel parking lot across from the existing Mews Centre remains open.
To ensure the safety of all users of the park please abide by signage in the area. A map of the impacted area is shown below:
-
New Design for H.G.R. Mews Centre Replacement Now Available
Share New Design for H.G.R. Mews Centre Replacement Now Available on Facebook Share New Design for H.G.R. Mews Centre Replacement Now Available on Twitter Share New Design for H.G.R. Mews Centre Replacement Now Available on Linkedin Email New Design for H.G.R. Mews Centre Replacement Now Available linkFrom now until September 25, the City of St. John’s invites the public to review the new concept design of the H.G.R Mews Community Centre replacement facility which will be constructed at Mundy Pond Park starting in 2021.
Public and stakeholder input from the first two rounds of public engagement for this project have influenced the overall design (check out the What we Heard documents in the document library). Details of the designs can be seen there as well including an aerial view and floor plans.
Virtual public meetings to review the design will take place using Microsoft Teams:
- Tuesday, September 22 from 10 to 11 a.m.
- Thursday, September 24 from 6:30 to 7:30 p.m.
To register for one of these sessions, check out the key dates and follow the links.
The city is also meeting with key stakeholders and users of the current facility such as sporting and aquatics organizations, the Boys and Girls Club, and the Inclusion Advisory Committee.
Those unable to participate online can contact Access St. John’s at 311 or 754-CITY and ask to speak with someone from the project team, or email feedback to engage@stjohns.ca.
-
Surveying Activity - Mundy Pond Park
Share Surveying Activity - Mundy Pond Park on Facebook Share Surveying Activity - Mundy Pond Park on Twitter Share Surveying Activity - Mundy Pond Park on Linkedin Email Surveying Activity - Mundy Pond Park linkCLOSED: This discussion has concluded.A survey crew will be in Mundy Pond Park starting Tuesday, Oct. 8, surveying the property where the new Mews Centre replacement will be located.
This work will take approximately four weeks and is scheduled to be completed by Tuesday, Nov. 5, weather permitting. As part of the scope of work, surveyors will be required to work in proximity to, and within property lines, that boarder Mundy Pond Park and vicinity.
-
What We Heard document released
Share What We Heard document released on Facebook Share What We Heard document released on Twitter Share What We Heard document released on Linkedin Email What We Heard document released linkCLOSED: This discussion has concluded.Public engagement on a proposed replacement location for the H.G.R Mews Community Centre at Mundy Pond Park took place during July 2019. Feedback from residents and community groups was collected at online, during two in-person sessions and through meetings with key stakeholders.
The ‘What We Heard" document summarizes overall themes, likes and dislikes of the proposed location, concerns outlined by local residents, feedback from community groups, and points related to inclusion. The engagement process captured input from 29 people online and approximately 80 visitors during the in-person sessions, with approximately 600 unique visitors to the engage page to learn more about the proposed location.
The first phase of public engagement for this project took place in spring 2018 and looked at programming, amenities and a proposed location at the gravel parking lot that is across the street from the current H.G.R. Mews Centre.
City Council are slated to vote on the location for replacing the Mews Centre on Monday, August 19.
-
Public Engagement: H.G.R Mews Community Centre Replacement New Proposed Site Location at Mundy Pond Park
Share Public Engagement: H.G.R Mews Community Centre Replacement New Proposed Site Location at Mundy Pond Park on Facebook Share Public Engagement: H.G.R Mews Community Centre Replacement New Proposed Site Location at Mundy Pond Park on Twitter Share Public Engagement: H.G.R Mews Community Centre Replacement New Proposed Site Location at Mundy Pond Park on Linkedin Email Public Engagement: H.G.R Mews Community Centre Replacement New Proposed Site Location at Mundy Pond Park linkCLOSED: This discussion has concluded.The public are invited to one of two engagement sessions to provide feedback on a new proposed site location for the replacement of the H.G.R. Mews Community Centre at Mundy Pond Park.
The city is proposing an alternate location to the gravel parking lot across from the current Mews Centre because of building needs, and the opportunity to position the facility in an existing recreation hub at Mundy Pond Park.
Please drop-in at your convenience to one of the two scheduled sessions for an opportunity to talk with staff about the potential location for the Centre, and to share your opinions and concerns.
Tuesday, July 30, 2019
· 10 a.m. to noon
· 6 to 8 p.m.
H.G.R. Mews Community Centre
40 Mundy Pond Road
Please note that the focus of the drop-in sessions is to obtain feedback about the new proposed site only. Public engagement about programming and amenities took place in 2018, and the ‘What We Heard’ document is available here.
Comments can also be provide on this page here.
The City of St. John’s wants to create a city where people feel connected, have a sense of belonging and are actively engaged in community life. This project is identified in the Our City, Our Future 2019 Action Plan under the goal to and deliver programs, service and public spaces that build safe, healthy and vibrant communities.
Follow Project
Document Library
- Updated Exterior Rendering May 2022 (2.17 MB) (png)
- Rendering - Gymnasium with Elevated Walking Track May 2022 (2.85 MB) (png)
- Rendering - Leisure Pool May 2022 (393 KB) (pdf)
- Rendered Views.pdf (8.34 MB) (pdf)
- Amenities Overview Mews Replacement.pdf (105 KB) (pdf)
- Mews Centre - Southwest Corner (2020-08-25).png (9.48 MB) (png)
- Mews Centre - Birds Eye View (2020-08-28).jpg (2.05 MB) (jpg)
- A-201 Level 1 Floor Plan.pdf (372 KB) (pdf)
- A-202 Level 2 Floor Plan.pdf (620 KB) (pdf)
- What we Heard document - August 2019 (612 KB) (pdf)
- What we Heard document - 2018 (620 KB) (pdf)
Project Schedule
-
Public Engagement Open
H. G. R. Mews Community Centre replacement has finished this stageThis consultation is Open for contributions.
-
Under Review
H. G. R. Mews Community Centre replacement has finished this stage -
What we Heard (July 2018) released
H. G. R. Mews Community Centre replacement has finished this stage -
Tender Awarded to Englobe
H. G. R. Mews Community Centre replacement has finished this stage -
Geotechnical work underway
H. G. R. Mews Community Centre replacement has finished this stage
-
Geotechnical work completed
H. G. R. Mews Community Centre replacement has finished this stage -
Public Engagement on new proposed location OPEN
H. G. R. Mews Community Centre replacement has finished this stage -
Feedback from consultation being reviewed
H. G. R. Mews Community Centre replacement has finished this stageStaff are reviewing all of the feedback.
-
What we Heard released - August 16, 2019
H. G. R. Mews Community Centre replacement has finished this stageThe What we Heard is available here
-
Council Decision - August 19, 2019
H. G. R. Mews Community Centre replacement has finished this stageOn Monday, Aug 19, City council voted in favor of the Mundy Pond Location for the replacement of the H.G.R Mews Centre. The Decision Note from the meeting is available here.
The Council agenda is online http://stjohns.ca/city-hall/about-city-hall/council-and-committee-minutes-and-agendas . Minutes will be posted following council’s adoption at next regular meeting on September 3rd.
-
Design Phase
H. G. R. Mews Community Centre replacement has finished this stageDesign plan shared with Council and public Sept. 2. 2020
-
Construction
H. G. R. Mews Community Centre replacement is currently at this stageConstruction began September 2021 and is set to continue until late Fall 2024.
-
New Building Open
this is an upcoming stage for H. G. R. Mews Community Centre replacementBuilding completion is anticipated to be late Fall 2024. More information pertaining to the Grand Opening will be posted here and on our other social media outlets as soon as it is available.
Who do I need to contact
-
Council Lead - Community Services
Phone 576-8363 Email soleary@stjohns.ca -
Manager- Facilities Engineering
Department of Planning, Engineering & Regulatory Services
TKEmail tknopp@stjohns.ca