Goulds Sewage Pumping Station Replacement Project


The Goulds Sewage Pumping Station is currently in the Commissioning stage until the end of October 2019.

Built by the Town of Goulds in 1983, the existing Goulds Sewage Pumping Station located at 557 Main Road has out lived its useful life and requires complete replacement. A new modernized facility will be built adjacent to the old facility and will convey the existing and future sewage flows for the Goulds area. This facility will be remotely monitored and operated through the Riverhead Wastewater Treatment Facility.

PROJECT FUNDING

The project was approved to receive cost shared funding on August 1, 2016 through the Clean Water and Wastewater Fund. The funding partners for this project are the Government of Canada, Province of Newfoundland and Labrador and the City of St. John's.

This page is not intended to replace other information such as Public Advisories or Public Notices (e- updates), for day to day updates such as traffic or water interruptions, etc. check the City's website. To keep informed of the city’s traffic advisories please sign up for e-updates at www.stjohns.ca.



The Goulds Sewage Pumping Station is currently in the Commissioning stage until the end of October 2019.

Built by the Town of Goulds in 1983, the existing Goulds Sewage Pumping Station located at 557 Main Road has out lived its useful life and requires complete replacement. A new modernized facility will be built adjacent to the old facility and will convey the existing and future sewage flows for the Goulds area. This facility will be remotely monitored and operated through the Riverhead Wastewater Treatment Facility.

PROJECT FUNDING

The project was approved to receive cost shared funding on August 1, 2016 through the Clean Water and Wastewater Fund. The funding partners for this project are the Government of Canada, Province of Newfoundland and Labrador and the City of St. John's.

This page is not intended to replace other information such as Public Advisories or Public Notices (e- updates), for day to day updates such as traffic or water interruptions, etc. check the City's website. To keep informed of the city’s traffic advisories please sign up for e-updates at www.stjohns.ca.


  • Construction started

    6 months ago
    CLOSED: This discussion has concluded.

    Construction has begun to replace the existing Goulds Sewage Pumping Station.

    The scope of the construction work will include deep excavation for the building foundation adjacent to the old facility. During this time there may be significant noise related to the excavation work. The City of St. John's apologizes for any inconvenience.


    Construction has begun to replace the existing Goulds Sewage Pumping Station.

    The scope of the construction work will include deep excavation for the building foundation adjacent to the old facility. During this time there may be significant noise related to the excavation work. The City of St. John's apologizes for any inconvenience.