Construction Schedule Update
The start date for construction of the Gleneyre Street Culvert Replacement project has been postponed. While initially planning to complete this work in 2022, construction is now expected to begin in the Spring of 2023 and be completed by November 2023.
The City had to revise the construction start-date due to a longer than anticipated lead time on the delivery of some items, which would have pushed construction outside the desired time frame for in-river works.
Construction was completed on November 3, 2023. Gleneyre Street was reopened to vehicular traffic on October 6, 2023.
Share Construction Schedule Update on Facebook
Share Construction Schedule Update on Twitter
Share Construction Schedule Update on Linkedin
Email Construction Schedule Update link
CONSTRUCTION COMPLETE, NOVEMBER 3, 2023
