Galway Village Green -Phase 1 Playground Development

Share on Facebook Share on Twitter Share on Linkedin Email this link

Galway Village Green Phase 1 - Playground Development began with a public RFP to hire a Landscape Architect in Summer 2021. The project was awarded in August 2021 and the consultant prepared tenders for public clearing and grubbing of the site as well as a topographic survey to aid in the Detailed Design Development which commenced in Fall 2021.

The Construction Tender has been awarded to Can-Am Platforms and construction commenced end of June 2022. The project will be completed in Spring 2023.

The Phase 1 development includes the following amenities: construction of a fully accessible 6500SF playground, a large multi-purpose court, a small picnic area, trails and pathways, landscaping, benches and seating, and a dedicated parking area.

Future phases of the development will include the following amenities: a splashpad, washrooms, maintenance shed, a community garden, a terraced garden, a pavilion, a large open green space, a performance stage area, a large picnic area, a viewing platform, and a seating area to overlook an engineered wetland. Further development of landscaping, park seating, pathways, and trails to provide connectivity to other amenities is planned for the area.


Galway Village Green Phase 1 - Playground Development began with a public RFP to hire a Landscape Architect in Summer 2021. The project was awarded in August 2021 and the consultant prepared tenders for public clearing and grubbing of the site as well as a topographic survey to aid in the Detailed Design Development which commenced in Fall 2021.

The Construction Tender has been awarded to Can-Am Platforms and construction commenced end of June 2022. The project will be completed in Spring 2023.

The Phase 1 development includes the following amenities: construction of a fully accessible 6500SF playground, a large multi-purpose court, a small picnic area, trails and pathways, landscaping, benches and seating, and a dedicated parking area.

Future phases of the development will include the following amenities: a splashpad, washrooms, maintenance shed, a community garden, a terraced garden, a pavilion, a large open green space, a performance stage area, a large picnic area, a viewing platform, and a seating area to overlook an engineered wetland. Further development of landscaping, park seating, pathways, and trails to provide connectivity to other amenities is planned for the area.


Q&A

You need to be signed in to add your question.

Page last updated: 27 Sep 2022, 11:58 AM